Menu

Crescent Valley

Crescent Valley aims to nurture students to become lifelong learners and responsible citizens. Crescent Valley students are prepared for life beyond high school through various educational opportunities.

CSD Bond logo transparent background

Project Information

What's Happening Now

January 2022

CVHS Renovation-Building F:

  • Updated – Overhead Door has provided a very soft ship date of Jan 10 for our new doors.
  • Our last couple of delayed security cameras are still scheduled to arrive at the end of January and install the first week of February. Camera angle review and adjustments continue as the school team gains familiarity with the new system.
  • Our commissioning agent, Elevate, continues to perform tests, developing trend logs and monitoring that the equipment operates as expected. Elevate, along with CSD’s help, continues to coordinate adjustments as these systems “learn” the new demand schedules. As we add new elements (exhaust fan units, VFD’s, relocated venting needs) to the project, these elements also roll into our new controls package.

Added scope items

  • Revised venting for the pug mill rooms was installed over winter break. At this time, we are all roughed-in and awaiting the new exhaust fan in late March.
  • We modified the kiln room venting to use 3 stand-alone enviro-vents exhausted through the roof individually. This work was completed over the winter break.
  • Relocation of 3 duct smoke detectors was accomplished over the winter break.
  • The revised layout for the metal shop equipment was moved forward over winter break. Existing equipment was relocated at the school’s request and the rough-ins for ventilation and power were also completed. The water jet should be installed in its new position this week.
  • Additional work remains to incorporate the two very large metal mills the school has acquired. Power and ventilation rough in for these units in their new locations has been completed.
  • Implementation of the new welding transformer and its associate electrical work by the contractor will occur throughout the month of January.
  • Work associated with the new emergency stop and total shop shut down buttons will also occur throughout the month of January.

View the January 2022 report here.

October, 2019: Design Development Continuing

The Building A boiler replacement project is complete.

The work on the athletic fields continues. The contractor has completed installing the synthetic turf. The track surfacing has begun and will continue as weather allows.

The design development phase is nearing completion and Pivot Architecture will begin working with staff on the final design details this fall.

Pivot Architecture is also working on a design for the seismic improvements and the team will apply for a $2.5 million State Seismic Grant this winter assuming the program rolls out as expected. Testing took place over the summer to gather more data on the condition of the existing building to better inform the requirements of planned seismic improvements.

The next Design Advisory Committee meeting will be held this fall.

September, 2019: Athletic Field Work Continues

The boiler replacement project is complete.

Work on the athletic fields continues with the installation of the synthetic turf this month. Track surfacing will begin once the turf installation is complete. Field improvements will be complete by November 2019. The design development phase is nearing completion and Pivot Architecture will begin working with staff on the final design details this fall.

Pivot is also working on design for the seismic improvements. The district will apply for a $2.5 million State Seismic Grant this winter.

Testing took place over the summer to gather more data on the condition of the existing building to better inform the requirements of planned seismic improvements. The next Design Advisory Committee meeting will be held this fall.

July-August, 2019: Athletic Facilities Improvements

The final base rock fine grading for the turf and final base rock prep for the asphalt at the new D zone work was installed the last week of August.

Paving will be the next step. Given the type of track materials used, the asphalt must cure for at least 28 days before the track surface can be laid.

The turf installation is scheduled to begin in September and will take approximately 3-4 weeks. That time frame could change as this is a weather-sensitive project.

Once the turf work is complete, the track surface will be laid and striped (also weather-sensitive).

We expect some rain in September and October so an estimated final completion date has not been established.

June, 2019: Summer Construction Activities Begin

Crescent Valley High School will have an artificial turf field installed and track resurfaced and the area will be closed to the public during construction.

Additional summer work includes the replacement of the boiler.

  • The CVHS track and infield will be closed to the public from June 21 through November 15.
  • Athletic practices will be relocated to other sites on the CV campus for the fall season.
  • Home football games will be played at Corvallis High School.

February, 2019: Initial site investigations and finalizing designs

Initial site investigations are underway, including topographical survey, hazardous material survey, geotechnical soil borings, seismic evaluation, and wetlands evaluation. Additionally, designs are being finalized for the field improvements and boiler replacement. Pivot Architecture is beginning work with the Site Team on initial planning and design. The Design Advisory Committee members and Site Team are being finalized.

Next quarter, Gerding Builders will receive subcontractor bids for the field improvements and boiler replacement. The boiler replacement will be completed summer 2019. Field improvements are scheduled to begin summer 2019 and to be completed in fall 2019.

November, 2018

Bond program managers are currently working on design and permitting for repairs and renovations.

Project Timeline

CVHS Elementary Bond Project Timeline

Bond Projects at CVHS

Crescent Valley was built in 1971. Crescent Valley’s current enrollment is 1,018, with a current capacity of 1,547.

Security camera icon transparent background Safety & Security Improvements

  • Enhance video surveillance system
  • Improve seismic safety
  • Increase power connections to generator circuit
  • Replace access control system
  • Replace emergency communication system

Light bulb icon transparent background Renovations & Repairs

  • Improve ADA accessibility
  • Install elevator in gym building for ADA access
  • Install a new artificial turf field
  • Refurbish, repair, and weatherize building exterior
  • Replace fire suppression system in kitchen
  • Resurface bus drop-off/pick-up lane
  • Resurface track
  • Upgrade mechanical infrastructure including electrical, heating, and plumbing systems

Computer icon transparent background Modernize Educational Spaces

  • Expand covered outdoor learning area for career and technical education
  • Renovate classroom spaces for career and technical education

Stay Informed about Bond Projects