Menu

Garfield Elementary

Garfield Elementary is a dual language immersion school that focuses on the needs of the whole child in a positive and caring learning environment.

CSD Bond logo transparent background

Project Information

What's Happening Now

October 2019: Land Use Application Submitted to City

The Land Use application has been submitted and is working its way through the City of Corvallis process. The date for the Planning Commission hearing has not yet been established.

The project team is working on the details of the construction phasing and a logistic plan. An updated project estimate was provided by Fortis Construction and did not change significantly from the previous estimate.

August 2019: Design Development Completed

The design team completed the Design Development and has met with staff to continue to work on the detailed aspects of the design. A neighborhood meeting was held on August 6 as part of the City of Corvallis Land Use approval process. The meeting was well attended with strong support for the project and the improvements to traffic flow, safety, and circulation.

A fourth Design Advisory Committee meeting was held on August 22 for committee members to review and provide feedback on the evolving design.

July 2019: Summer Design Work

The design team is working on design development over the summer so they will be ready to re-engage with staff this fall to continue to work on the more detailed aspects of the design. A very productive all day design review session was held the week before the summer break. The design team reviewed all aspects of the current design with school and facilities staff to receive input and answer questions so the design work could continue during July and August and proceed on schedule. The schematic design estimate for the bond promise scope exceeded the original Garfield budget. The Bond Leadership Team has authorized the use of bond reserve funds if needed, to complete the planned projects.

The Garfield Design Advisory Committee will meet on August 22 for meeting #4.

El equipo de diseño está trabajando en el desarrollo del diseño durante el verano por lo que estarán listos para reunirse con el personal éste otoño, para continuar trabajando en los aspectos más detallados del diseño. Antes de las vacaciones de verano, se llevó a cabo una reunión de revisión del diseño muy productiva. El equipo de diseño revisó todos los aspectos del actual diseño con personal de las escuelas y del distrito para conocer su opinión y responder preguntas para que el equipo de diseño pudiera continuar su trabajo durante julio y agosto según lo programado. Lo estimado para el diseño esquemático excedió el presupuesto original para Garfield. El equipo líder del bono ha autorizado el uso de fondos de reserva, de ser necesario, para completar los proyectos planeados. 

April, 2019: Design Advisory Committee Update

This project will expand Garfield from 46,000 square feet to 62,000 square feet including four additional classrooms, student support spaces, and an art and science classroom. In March, a preliminary site diagram concept was presented for feedback. The concept featured a number of site improvements:

  • Additional classroom wing added on the north side of the school, adjacent to the current gymnasium
  • Reconfigured and expanded front entrance and office area
  • Reconfigured site circulation and an increase of parking spaces

The proposed siting of the new classroom wing is based on the design guidance principles that will be used throughout the bond program; specific to the Garfield site:

  • a north facing classroom orientation provides better daylighting and efficiencies in heating/cooling
  • efficient internal circulation and room adjacencies
  • consolidation of outdoor learning and play areas and safety site lines

Este proyecto ampliará las instalaciones de Garfield de 46,000 pies cuadrados a 62,000 pies cuadrados, incluyendo cuatro salones de clase adicionales, espacios de apoyo para estudiantes y un salón de clases para arte y ciencia. En la reunión del  mes de marzo, se presentó un diagrama del concepto de manera preliminar para recibir retroalimentación. El concepto presentó una serie de mejoras en el sitio:

  • Ala adicional con aulas en el lado norte de la escuela, adyacente al gimnasio actual
  • Zona de entrada y oficina reconfigurada y ampliada
  • Reconfiguración de la circulación del sitio y un aumento de los espacios de estacionamiento (esto está en la etapa inicial del proceso y aún está sujeto a la revisión de las autoridades de la ciudad)

La ubicación propuesta para la nueva ala con aulas se basa en los principios que guían el diseño y que se utilizan en todos los proyectos financiados por el bono; específicos a Garfield son:

  • Aulas orientadas hacia el norte proporcionan una mejor iluminación natural y eficiencia en calefacción / refrigeración
  • Circulación interna eficiente y espacios adyacentes
  • Consolidación de áreas de juego y aprendizaje al aire libre y líneas de seguridad del sitio

February, 2019: Design and communication

Communication protocol has been established between Wenaha and main office staff at Garfield. Additionally, design is underway.

Activities scheduled for next quarter involve two Design Advisory Committee meetings and a proposal from the geotechnical team.

Se ha establecido un protocolo de comunicación entre el Grupo Wenaha y el personal en la oficina de la escuela primaria Garfield. Además, el diseño está en marcha.

Las actividades programadas para el próximo trimestre incluyen dos reuniones del Comité Asesor de Diseño y una propuesta del equipo geotécnico.

January, 2019: Design Work Begins

The design phase for our school will begin in January 2019. Construction is scheduled to begin in September 2019. We will share regular updates and opportunities for input.

La fase de construcción para nuestra escuela comenzará en enero de 2019. La construcción está programada para comenzar en septiembre de 2019. Vamos a compartir las actualizaciones constantemente y las oportunidades para su aporte.

November 18, 2018: Garfield Design Advisory Committee

The Design Advisory Committee has been selected. Members include Justin Azhocar, Claudia Bouvier, Yazmin Brambila, Lupita Cobian, Nancy Davila-Williams, David Harner, Maria Hernandez, Elvira Huidor-Dever, Savannah Laney de Battro, Cathy Law, Perla Martinez, Daniel Olvera, Mara Silvera, Tammy Woodman, Maria Wright, Leigh Santy, and a representative from district.

This committee will ensure that the values of the school community are represented in the design and that the school community will be kept informed throughout the design and construction process.

El Comité Asesor de Diseño ha sido seleccionado. Los miembros incluyen Justin Azhocar, Claudia Bouvier, Yazmin Brambila, Lupita Cobian, Nancy Davila-Williams, David Harner, María Hernández, Elvira Huidor-Dever, sabana Laney de Battro, Cathy Law, Perla Martinez, Daniel Olvera, Mara Silvera, Tammy Woodman, María Wright, Leigh Santy, y un representante del personal del distrito.

Este Comité asegurará de que los valores de la comunidad escolar se representen en el diseño y que la comunidad escolar se mantenga informada durante todo el proceso de diseño y construcción. La fase de diseño para nuestra escuela comenzará en enero de 2019.

November - December, 2018: Architect Review and Site Surveying

Pre-design work at Garfield is taking place including a site walk-through by the architect team. The site is also being surveyed as part of the pre-design process.

El trabajo de diseño previo en Garfield se está llevando a cabo incluyendo un recorrido por la obra por el equipo del arquitecto.  La obra está siendo inspeccionada como parte del proceso de diseño previo.

 

November 5, 2018: Design Advisory Committee

The Garfield Design Advisory Committee will be announced and meetings will get started in January 2019.

Se anunciará el comité asesor de diseño de Garfield y las reuniones se iniciarán en enero de 2019.

Project Timeline

Garfield bond timeline

Garfield Spanish bond timeline

Bond Projects at Garfield

Garfield Elementary was built in 1955. Garfield’s current enrollment is 444, with a current capacity of 468.

Security camera icon transparent background Safety & Security Improvements

  • Enhance emergency communication systems
  • Improve playground lighting
  • Improve seismic safety
  • Improve site circulation and parking
  • Replace sidewalks
  • Secure front entry and office modifications

Construction icon transparent background Capacity Improvements

Garfield’s current capacity is 468. The projected new capacity is 531.

  • Add six permanent classrooms
  • Renovate four existing classrooms for student support services
  • Remove three portable classrooms

Light bulb icon transparent background Renovations & Repairs

  • Add a covered play shelter
  • Improve ADA accessibility
  • Install energy efficient lighting
  • Renovate restrooms
  • Repair concrete floor foundation
  • Upgrade finishes in hallways and shared spaces, including floors, paint, and ceilings
  • Upgrade mechanical infrastructure, including electrical, heating, and plumbing systems
  • Replace kitchen flooring

Computer icon transparent background Hands-On Learning Modernization

  • Create collaborative/small group learning areas
  • Expand library/media center
  • Relocate school garden for construction, if necessary

Photos

Garfield design committee photo

Design Advisory Committee meeting

Stay Informed about Bond Projects