Menu

Lincoln Elementary

Lincoln Elementary is a dual language immersion school that prioritizes developing an increased cultural awareness while learning a second language.

CSD Bond logo transparent background

Lincoln Elementary

What's Happening Now

October 2019

Design Development is approaching 100%.  The District, Wenaha, JLD Estimating and DLR are reviewing estimates and designs to reconcile with the budget. 

Initial land use submission has been made and we are waiting for Planning Department feedback prior to final submission.

The Benton County Health Clinic project continues in the design process with estimating about to start.

August 2019: Design Development Near Completion

Two neighborhood meetings were held including a meeting on August 29 as part of the City of Corvallis Land Use approval process. Both meetings were well attended with positive comments and input provided.

Design Development is at 90%.  The bond team is reviewing these documents and JLD Estimating is preparing cost estimates. 

The Benton County Health Clinic project, which is being developed through an Intergovernmental Agreement, is in design and will be submitted to the Planning Department with the school project.  At present, the County has committed funding through the design process.  By the end of the calendar year, they are to notify the District if they are committed to building the facility.

A package is being prepared by Willamette Valley Planning and will be submitted to the City of Corvallis Planning Department for consideration.

July 2019: Summer Design Work

Design Development is in process. Focus groups with teachers, administrators and specialists took place in June to inform the design team’s summer work. This input was used as designs were developed and will be reported back to the Focus Groups after the summer break. The Lincoln site plan is fairly solid, with design work starting on the County Health Clinic, in coordination with Benton County. This design work is being done utilizing the district’s design team, with reimbursement from the county. Approval of final design is expected this fall, with construction cost approval pending bid in early 2020.

El desarrollo del diseño está en proceso. Grupos de enfoque con maestros, administradores y especialistas, se llevaron cabo en junio para informar acerca del trabajo del equipo de diseño durante el verano. Sus aportaciones se utilizaron para desarrollar el diseño y se reportará de regreso a los grupos de enfoque después de las vacaciones de verano. La propuesta para Lincoln es bastante sólida, con trabajo de diseño iniciando en la clínica de salud del condado, en coordinación con el condado de Benton. Este diseño se está realizando utilizando el equipo de diseño del distrito, con reembolso del condado. Se espera la aprobación final del diseño para este otoño, con el costo de construcción pendiente a licitación al inicio del 2020. 

May 2019: Design Advisory Committee meeting #3

The core team meets regularly and includes the architects, Principal Hale, Kim Patten, and Amy Lesan. The core team develops the designs that are brought to the DAC meetings for feedback.

  • The current site concept includes a parking and parent drop-off area adjacent to 99W and a private drive on the east side of the site for bus drop-off (only). This would require the relocation of the tennis courts.
  • The new building includes collaboration spaces adjacent to classrooms. There are a variety of collaboration space designs.
  • Primary grades will be located on the first floor, the library, learning resource center and grade 2-5 classrooms will be upstairs.

View the site concept HERE.

Esta es la tercera reunión para el Comité Asesor de Diseño (DAC) para Lincoln. El equipo central se reúne regularmente e incluye a los arquitectos, el director Hale, Kim Patten y Amy Lesan. El equipo central desarrolla los diseños que se llevan a las reuniones del Comité Asesor de Diseño (DAC) para su retroalimentación.

  • El concepto actual del sitio incluye un estacionamiento y un área para que los padres puedan dejar a sus hijos desde el auto, junto a 99W y una entrada privada en el lado este del sitio solo para autobuses. Esto requerirá la reubicación de las canchas de tenis.
  • El nuevo edificio incluye espacios de colaboración adyacentes a las aulas. Hay una variedad de diseños de espacios de colaboración.
  • El jardín de niños y primer grado se ubicarán en el primer piso, la biblioteca, el centro de recursos de aprendizaje y los salones de segundo a quinto grado estarán en el segundo piso.

February, 2019: Design Advisory Committee meeting and design process

The first Design Advisory Committee meeting is February 20 at 6 pm at Lincoln Elementary. Additionally, a civil engineer has toured the site. Design is in progress and first Core Team meetings are underway.

Activities scheduled for next quarter include City of Corvallis land use and permitting meetings, as well as site observation for wetlands on the site.

La primera reunión del Comité Asesor de Diseño es el 20 de febrero a las 6 pm en la escuela primaria Lincoln. Además, un ingeniero civil ha recorrido el edificio. El diseño está en proceso y las primeras reuniones del equipo central están en curso.

Las actividades programadas para el próximo trimestre incluyen el uso de la tierra en la ciudad de Corvallis, reuniones para los permisos, asi como la observación de humedales en el área.

January, 2019: Lincoln Design Advisory Committee

The Design Advisory Committee will begin meeting in January and will be facilitated by project architects.

El Comité Asesor de Diseño comenzará a reunirse en enero y el equipo del arquitecto lo facilitarán.

November - December 2018: Architect Review and Site Surveying

Pre-design work at Lincoln is taking place including a site walk-through by the architect team. The site is also being surveyed as part of the pre-design process.

El trabajo de diseño previo en Lincoln se está llevando a cabo incluyendo un recorrido por la obra por el equipo del arquitecto.  La obra está siendo inspeccionada como parte del proceso de diseño previo.

November, 2018: Design Advisory Committee

The Design Advisory Committee has been selected. Members include Sonya Bacheller, Patricia Cabeza, Aliesje King, Thom King, Aaron Lesan, Denna Melton, Araceli Mendez, Dana Monroe, Alison Ocampo Maria Rosas, Shahnaz Sahnow, De Nyago Tafen, Cecelia Tellez, Rebecka Weinsteiger, Julie Wilborn, Principal Hale, and a representative from district staff.

This committee will ensure that the values of the school community are represented in the design and that the school community will be kept informed throughout the design and construction process.

El Comité Asesor de Diseño ha sido seleccionado. Los miembros incluyen Sonya Bacheller, Patricia Cabeza, Aliesje King, Thom King, Aaron Lesan, Denna Melton, Araceli Mendez, Dana Monroe, Alison Ocampo Maria Rosas, Shahnaz Sahnow, De Nyago Tafen, Cecelia Tellez, Rebecka Weinsteiger, Julie Wilborn, Principal Hale, y un representante del personal del distrito.

Este Comité asegurará de que los valores de la comunidad escolar se representen en el diseño y que la comunidad escolar se mantenga informada durante todo el proceso de diseño y construcción. La fase de diseño para nuestra escuela comenzará en enero de 2019.

Project Timeline

Lincoln bond timeline

Lincoln Spanish bond timeline

Bond Projects at Lincoln

Lincoln Elementary was built in 1949. Lincoln’s current enrollment is 387, with its capacity at 489.

Construction icon transparent background Replace School on Current Property

  • Construct on the southeast corner of the current property
  • Students would continue to attend Lincoln Elementary during construction
  • Public tennis courts would remain at the current location UPDATED spring 2019: courts will need to be relocated to a new site
  • Lincoln Health Clinic will continue to be located on the school campus
  • Design process would begin immediately and include collaboration with community and staff

Security camera icon transparent background Safety & Security Improvements

  • New emergency communications system
  • Built to current seismic safety codes
  • Well-designed parking and site circulation

Light bulb icon transparent background Sustainability

  • Sustainable design
  • Maximize daylighting
  • Install energy efficient building systems

Computer icon transparent background Modern Educational Spaces

  • Learning spaces for small group, collaboration, and project based learning
  • Outdoor learning including school garden and outdoor play areas
  • Separate multi-purpose dining commons and gymnasium
  • Planned spaces for student support services

Photos

Lincoln committee photo

Design Advisory Committee

Lincoln committee photo 2

Design committee reviewing the concept plan

photo of community meeting

Lincoln neighborhood meeting (8/13/19)

Lincoln neighborhood meeting

Neighborhood Land Use Meeting (8/29/19)

Live Camera

Coming in Spring 2020!

Stay Informed about Bond Projects