Menu

Jefferson Elementary

Jefferson Elementary provides a solid educational foundation to K-5 students with a focus on high achievement in reading and math. Jefferson also has the Life Skills program, which provides a highly structured learning environment to students who may need additional support.

CSD Bond logo transparent background

Project Information

What's Happening Now

March 2020

DLR Group submitted a draft version of the schematic design report for this project to the District on February 14. The final version of the schematic design book will be presented to the District on March 6.

Fortis will use the month of March to dive deep into the Schematic Drawings to determine cost impacts, constructability detail reviews, and value-engineering options. This early design period is an essential time to help set the direction for success. Although there are similarities between the schools, each has unique characteristics that deserve special attention. Fortis anticipates issuing a comprehensive cost model for each of the three schools in early April.

Core Team meeting #5 will be held March 6. Principals and Office Managers will provide input on the updated designs for the additions and renovations.

As part of the State Historic Preservation Office (SHPO) requirements, a graphic display is being assembled. Students at CHS are working to produce a permanent display that represents an interpretation of the site and building history. Current and past Jefferson students will be asked to document what they have learned about their school’s history and how it connects to the surrounding community.

February 2020: DLR Group working on schematic design phase

DLR Group is working on the Schematic Design phase of the project for work scheduled to start in the spring of 2021.

The Design Advisory Committee meeting #1 was held January 29. DAC members from Adams, Jefferson and Wilson came together as a group to discuss the bond program and then broke out into individual groups by school to review and comment on their school designs.

Part of the process of renovations and additions includes The State Historic Preservation Office (SHPO) for structures that were built more than 50 years ago. Some projects are granted clearances, but Jefferson was deemed to be of historical importance. The District worked with Archaeological Investigations Northwest to develop an Oregon State Level Documentation report for Jefferson, and a mitigation agreement is in place which among other things, provides for a unique student participation opportunity to produce a permanent display that represents an interpretation of the site and building histories.

January 2020

DLR Group is working on the Schematic Design phase of the project for work scheduled to start in the spring of 2021. The Design Advisory Committee meeting #1 is scheduled for January 29.

The DAC meetings will be joint meetings between Jefferson, Adams, and Wilson.

November 2019: Design Advisory Committee Meetings to Begin in January

The DLR Group architect team is preparing to initiate the design processes of the next phase of work scheduled for spring of 2021.  Design Advisory Committee members are being sought. 

This project is being managed in parallel with Wilson and Adams.  There will be shared design efforts, as well as site-specific work.

Core Team meetings (including the bond team and building principals and office managers) kicked off on November 1.  The proposed bond scope was reviewed and input was provided on the initial design concepts for the addition and renovation.

September 2019: Design Process to Begin

Seismic work was completed before the start of the new school year. DLR Group, the project architect, is preparing to initiate the design processes of the next phase of work still scheduled for the spring of 2021. The bond team is working on a plan for community and staff involvement.

August 15, 2019

Fortis is making great progress with construction activities and remains on track despite the unforeseen items that come with remodels. Some of the unforeseen items include equipment or ductwork in the way of new seismic braces or clips or heaters/HVAC that needed to be removed off an entire wall length rather than just a small section due to the original construction.

This project is still on schedule and within budget.

June 2019: Seismic Upgrade Construction Begins

Jefferson will be closed from June 21 through August 25 for seismic upgrade construction work.  The office will temporarily be relocated to a modular classroom. Summer hours will be announced.

February, 2019: Site tours and finalizing investigation process

Site tours by the design team are in progress. Additionally, we are finalizing the design engineer’s investigation process with documentation. Seismic upgrade design work is also in progress.

Activities scheduled for next quarter include hazardous material sampling and testing and continued pre-design.

December 2018: Site walk-throughs completed

Site walk-through by the project team and structural engineers.

October 15, 2018: Seismic Design & Permitting

Bond program managers are currently working on design and permitting for seismic projects to be completed at Jefferson Elementary this summer.

Project Timeline

Jefferson bond timeline

Bond Projects at Jefferson

Jefferson Elementary was built in 1960. Jefferson’s current enrollment is 351, with a current capacity of 383.

Security camera icon transparent background Safety & Security Improvements

  • Improve seismic safety
  • Replace emergency communication systems
  • Secure front entry and office modifications
  • Improve emergency lighting
  • Improve sidewalk & site circulation

Construction icon transparent background Capacity Improvements

  • Add three permanent classrooms, remove portable classrooms
  • Renovate classrooms for student support services

Light bulb icon transparent background Major Repairs

  • Upgrade mechanical infrastructure
  • Upgrade finishes in hallways and shared spaces including floors, paint, and ceilings
  • Improve ADA accessibility
  • Install energy efficient lighting
  • Replace covered play shelter

Computer icon transparent background Modern Educational Spaces

  • Create collaborative/small group learning areas
  • Create dedicated PE space by adding multi-use cafeteria

Photos

Coming soon!

Stay Informed about Bond Projects