Project Information
What's Happening Now
April 2023
Admin Addition:
- All interior walls have been sheetrocked and presently being taped. Painting to commence when complete.
- Roofing is complete.
- All ceilings commence as soon as the walls have been painted.
- All MEP rough in has been completed and finish will commence when walls painted, and ceiling grid installed.
- Exterior – waterproofing, window flashings and windows presently being installed.
- Scheduled to be completed in May.
Art/Science Addition:
- A roof membrane has been installed and the remaining roofing will be completed when weather allows. The building is dried in.
- MEP rough is progressing.
- Exterior – waterproofing, window flashings and windows presently being installed.
- Scheduled to be completed before the end of school year.
Sector B Classrooms (Existing Building)
- Turned over at Spring Break.
View the April 2023 report here.
October, 2019
Construction is scheduled to begin in the spring of 2022.
February, 2019: Building walk-through and investigation
A building walk-through is in progress to observe existing conditions. An investigation of the existing building and surroundings is also underway.
Hazardous material sampling and testing will occur next quarter.
Project Timeline
Bond Projects at Mt. View
Mt. View Elementary was built in 1954. Mt. View’s current enrollment is 319, with a current capacity of 468. The projected new capacity is 446.
Safety & Security Improvements
- Relocate and secure front entry and office
- Enhance emergency communication systems
- Improve site circulation and parking
- Improve emergency lighting
- Improve seismic safety
Capacity Improvements
Mt. View’s current capacity is 468. The projected new capacity is 446.
- Add three permanent classrooms
- Remove four portable classrooms
Renovations & Repairs
- Upgrade mechanical infrastructure including electrical, heating, and plumbing systems
- Upgrade finishes in hallways and shared spaces including floors, paint, and ceilings
- Improve ADA accessibility
- Install energy efficient lighting
- Replace kitchen flooring
Modernize Hands-On Learning
- Create collaborative/small group learning area
- Relocate school garden